Poplar Manor Cambridge
Follow us here for updates on the build.
All visual CGI rendering are for illustration only, completed work are determined by customer customisation etc.


.jpg)
.jpg)
.jpg)

.jpg)
.jpg)
.jpg)

.jpg)
.jpg)

13 06 2023
Site Setup
07 09 2023
Team move in


07 10 2023
Existing building repair
04 07 2024
Buildings repaired


08 07 2024
Footings reinforcement
16 08 2024
Site clearance


01 10 2024
Bad rain
25 10 2024
Structural repair


06 11 2024
Structural repair
25 11 2024
Phase 1 structure repair complete


04 12 2024
6 inch drainage installed
27 12 2024
Scaffolding erecting


13 01 2025
Casting 18inch floor slab with 3 layers of reinforcement meshes
16 01 2025
Posi-joists install


11 02 2025
Roof steels erection
17 03 2025
Roof steel structure complete


21 03 2025
Roof purlin erection work begin
21 03 2025
1st floor external timber frame infill complete